Abstract: Practical, field-tested guidance for selecting and running a concrete recycling crusher line. This paper explains definitions, working principles, structure, drive & power matching, key parameters (crushing ratio, chamber type, CSS/OSS, rotor speed, motor power), typical equipment combinations, expected throughputs, feed / product size ranges, and real-world operation notes. The content is based on verified product data and application notes from contemporary recycling crusher literature, and on typical on-site experience; therefore the recommendations below are direct, decisive, and designed for operators and project managers who need dependable outcomes, not marketing fluff.
Concrete recycling crushing means converting demolished or cast concrete blocks and debris into graded aggregate for reuse. The goal is to produce reusable aggregate fractions and sand, and to remove contaminants like rebar. This process reduces disposal cost, and supplies material for road base, fill, and new concrete mixes. The machines used range from fixed jaw primary crushers to mobile impact or cone secondary/tertiary crushers, plus screening and rebar separation units. The selection depends on feed size, contamination level, and the desired end product; moreover, mobility and footprint limits often decide the plant layout. :contentReference[oaicite:0]{index=0}
Primary reduction usually uses a jaw crusher. The machine bites large blocks and compresses them between a fixed and a moving jaw. The eccentric shaft drives the moving jaw. That action breaks the material into smaller particles. Secondary reduction frequently uses impact or cone machines. Impact crushers use high-speed rotor impact to fracture brittle concrete; cone crushers use compressive and gyratory action for finer grading and lower fines generation. Screens separate sizes while magnets and presifters remove rebar and metal. Each stage must be matched: feed size into the secondary must be within the secondary’s allowable feed window; otherwise throughput drops and wear rises.
The typical concrete recycling train contains: feeder, primary jaw crusher, secondary impact or cone crusher, vibrating screens, conveyors, magnetic separators, and dust suppression. Drives are either direct motor-to-gearbox or belt-driven; electric motors are the norm on fixed sites; diesel packs or hybrid electric systems suit mobile plants. Key components are the crushing chamber, eccentric shaft, rotor or mantle, wear liners (jaw plates, blow bars, concaves), bearings, and hydraulic adjustment or tramp relief systems. The crushing chamber geometry (cavity profile) dictates particle shape and crushing ratio. Proper motor sizing and soft start control prevent torque shocks and protect the supply network. {index=2}
Definition: The ratio of feed size to product size. For a jaw crusher, a practical reduction ratio is 6:1 in most applications. Exceeding this ratio risks poor performance and premature failure. Keep the ratio conservative for mixed, reinforced concrete.
Chamber / cavity shapes: deep cavities allow coarse feed and high reduction; shallow cavities aid finer product and better shape. For recycling, choose a cavity that lets rebar and spaced aggregates pass without blockage, yet still gives a good bite. Changing liner profiles alters product gradation and wear patterns. :contentReference[oaicite:4]{index=4}
CSS (jaw/cone) or OSS (impact) sets the minimum gap at which crushed material exits. Small CSS = finer product and lower throughput; large CSS = coarser product and higher throughput. For concrete recycling, set CSS to deliver the target coarse fraction for aggregates and allow a downstream impactor or sand maker to shape the finer material. Always log CSS adjustments and correlate with throughput and energy use.
Impact crushers’ rotor speed is pivotal. High speed increases impact energy and fines; lower speed favors coarser aggregate and less wear. Typical motor speeds in commercial impact machines are around 2,000 RPM for the main rotor. Match motor power to expected peak torque, plus 20-30% reserve for tramp events and start-up. Under-powering causes stalling; over-powering wastes energy. :contentReference[oaicite:6]{index=6}
Wear part lifetime depends on feed abrasiveness and operating practice. For impact blow bars, a service life near 300 hours is a practical expectation in recycled concrete work, if mix includes aggregates and sand. Jaw plates may last longer but require rotation and re-profiling. Plan planned maintenance every 250–500 operating hours for inspection, and major overhauls at 3,000–6,000 hours depending on heavy use. Track life hours and adjust spare parts inventory accordingly.
Concrete feed sizes vary. For demolished blocks, expect 50–800 mm lumps. Here are practical target stages: primary jaw to reduction ~500→65–160 mm; secondary impact to 0–40 mm fractions for sand and fine aggregate; screening separates 0–4, 4–10, 10–20, 20–40 mm bins. Example model data used in planning: a commonly used PE900×600 jaw has capacity up to ~150 t/h when fed with suitable material and set to typical CSS ranges. Mobile impact plants can be configured to serve 50–300 t/h ranges depending on model and feed. These capacity bands guide plant sizing decisions.
Below is a pragmatic equipment stack that has proven reliable on urban demolition sites. The items are generic descriptors referencing contemporary recycled-concrete machinery specs and roles. Do not read brand names here; treat these as functional parts.
Function: regulate feed; remove oversize or undesirable fines; protect crusher from tramp. Capacity: sized for 100–150 t/h feed. Install a metal detector or magnet upstream.
Role: first break of large blocks. Typical feed size up to 500 mm. Typical nominal capacity for PE900×600 style machine: ~80–240 t/h depending on CSS and material. Motor power example: ~75 kW for medium duty. Reduction ratio typical 6:1.
Role: shape and reduce to required gradations. Feed size ≤400 mm. Rotor speed ~2,000 RPM; typical outputs: 0–7, 7–15, 15–20 and 20–40 mm fractions. Plan blow bar change intervals near 300 hours under heavy abrasive feed.
Role: sort product sizes. Typical screen cuts at 4 mm, 10 mm, 20 mm. Oversized returns to secondary crusher. Choose screen type and deck angle to reduce pegging when fines are present.
Role: remove steel; shear or eject rebar. Essential to protect crushers and improve product purity. Place after primary and before final screening.
Role: reduce dust and wash fines for concrete sand; helps reach specifications for engineered fill. Expect water handling and settling considerations on site.
From projects and machine data, expect machine electrical consumption approximately proportional to throughput. For a 100 t/h plant with a 75–160 kW main motor bank plus auxiliary drives, typical average grid demand is 150–350 kW depending on how many units run concurrently. Energy per tonne depends on feed and target product; realistic ballpark for medium hard concrete lies between 0.8 and 3.5 kWh/t; softer mixes at the lower end, highly reinforced mixes higher. Track real site numbers; estimate first, then measure.
Downtime drivers: feed gating, rebar entanglement, wear-part failure, and improper CSS settings. Typical unplanned failure rates on well-operated plants can be kept under 4–7% of operating hours. Planned maintenance windows every 250–500 hours reduce the risk of unplanned stops. Keep a spare set of wear parts for the primary and secondary on site. For blow bars, keep at least 2–3 spare sets for continuous operation.
Case highlight A — urban demolition feed with medium rebar content: A mobile jaw + impact train was used. Pre-screening and a magnet ahead of the jaw avoided repeated stoppages. CSS kept slightly wider at first, then closed when the rebar ratio dropped; this balance saved wear and gave steady output. Operators logged wear hours and scheduled hammer swaps overnight. The plant averaged 90 t/h during 12-hour shifts.
Case highlight B — slab recycling and sand production: A compact impactor with an integrated screen produced a usable 0–4 mm sand wash fraction. The plant used water recycling and a compact settling tank. Maintenance: daily visual checks, weekly blow bar inspections, and monthly rotor balancing minimized vibration issues. These practical steps are repeatable and low cost.
Measure maximum lump size, average lump size, rebar content, and contamination (soil, wood). If lumps exceed 600 mm, a primary jaw is mandatory. If rebar >10% by volume, plan robust rebar extraction lines.
Do you need structural-grade aggregate, or just fill? For engineered concrete reuse, use a two-stage jaw+cone/impact circuit with washing. For fill, a single stage plus screen can be enough.
Mobile plants reduce transport and site setup. Fixed plants are more energy efficient and better for long-term, high-throughput operations. Evaluate payback on transport, setup time, and local permitting.
Confirm grid capacity or diesel availability. Size main motors with 20–30% surge margin for reliability. Include soft-starters or VFDs to reduce inrush and to allow smoother torque control.
Prefer vendors with documented quality systems and international certifications. Such credentials reduce risk and usually mean better factory testing and spares support.
Result: chokings and low yield. Avoid by matching secondary feed size to rated feed size of the crusher. Use a feeder to normalize lumps.
Result: heavy wear and shaft damage. Solution: install magnets and a rebar shear, and train staff to inspect feed.
Excess fines lower value of product and raise washing cost. Control by adjusting rotor speed, CSS, and using a staged crushing approach.
Throughput (t/h), feed gradation, product gradation, energy consumption (kWh/t), wear hours of key parts, unplanned stops, CSS settings, and maintenance actions. Keep a simple logbook or digital record. Over three weeks you will have sufficient data to optimize settings and spare parts planning. Monitoring reduces operating cost and increases uptime materially.
Crushing generates dust and noise. Use water suppression, enclosed conveyors, and acoustic enclosures when operating in urban sites. Manage wash water and sediments according to local regulation. Provide PPE and enforce rebar handling precautions. These measures are not optional for long-term operations.
For reliable recycling of concrete blocks, choose a practical two-stage approach: robust jaw primary and shape-oriented impact secondary, with screening and magnetic separation. Size the plant to expected average throughput, not peak spikes. Keep wear parts inventory on hand and track hours. Prioritize vendors that demonstrate factory testing and recognized quality certifications. On the site side, train operators to manage CSS and rotor speed, and to remove rebar upstream. These steps cut energy use, lower downtime and deliver consistent, saleable aggregate.
Yes / No
Yes / No
Yes / No
Yes / No
I have seen many sites where simple, conservative choices; plus a disciplined maintenance routine, made the difference between a profitable plant and perpetual trouble. Choose robust components, set realistic CSS values, keep the feed clean, and record every hour. These practices always win. The technical rules above are actionable and field-tested; follow them strictly for repeatable results.
We value your feedback! Please complete the form below so that we can tailor our services to your specific needs.